Polychem wants Stateline to pick up and transport waste products from
its six plants to three waste disposal sites. The chemical wastes that
will be hauled can be hazardous to humans and the environment if they
leak. A number of towns and communities in the region where the plants
are located prohibit hazardous materials from being shipped through
their municipal limits. Shipments must be handled carefully and
transported at reduced speeds and traverse circuitous routes.
Calculations for cost of shipping a barrel from each of the six plants
to each of the three disposal sites is:
WASTE DISPOSAL SITE
Plant Whitewater Los Canos Duras
Kingsport
$12
$15 $17
Danville 14
9 10
Macon
13
20 11
Selma
17 16 19
Columbus
7
14 12
Allentown
22 16 18
Click here to have a similar paper done by a professional writer..................Order and get a 100% original high-quality custom paper within the set deadline.
The plants generate the following amounts of waste products each week:
PLANT WASTE PER WEEK (bbl)
Kingsport 35
Danville 26
Macon 42
Selma 53
Columbus 29
Allentown 38
The three waste sites of Whitewater, Los Canos and Duras can accommodate
a maximum of 65, 80, and 105 barrels per week respectively.
The manager is considering using each of the plants and waste disposal
site as intermediate shipping points. Trucks would be able to drop a
load at a plant or disposal site to be picked up and carried to the
final destination by another truck and vice versa. Stateline would not
incur any handling costs because Polychem has agreed to take care of all
local handling of the waste materials at the plants and the waste
disposal sites. The only cost Stateline incurs is the actual
transportation cost. The manager wants to consider the possibility that
it may be cheaper to drop and pick up loads at intermediate points
rather than ship them directly. The estimated shipping costs per barrel
between each of the six plants is:
PLANT Kingsport Danville Macon Selma Columbus Allentown
Kingsport $____
$6 $4 $9
$7 $8
Danville $6
_____
11 10 12 7
Macon $5
11 _____ 3
7 15
Selma $9
10 3 ____
3 16
Columbus $7
12 7 3
____ 14
Allentown $8
7 15 16
14 ____
the estimated shipping cost per barrel between each of the three waste disposal sites is:
WASTE DISPOSAL SITE WHITEWATER LOS CANOS DURAS
Whitewater $______ $12 $10
Los Canos $12 $___ $15
Duras $10 $15 $___
The manager wants to determine the shipping routes that will minimize
Stateline's total cost in order to develop a contract proposal to submit
to Polychem for waste disposal. She wants to know if it would be
cheaper to ship directly from the plants to the waste site or if she
should drop and pick up some loads at the various plants and waste
sites. Develop a model to assist the manager and solve the model to
determine the optimal routes.
SHOW THE WORK!